Assist during disassembly and reassembly of TG1 centerline instrumentation. The scope of work for this effort is outlined below:
- disassembly, inspection and install
- Vibration Probe removal/install – (T1,T2, T3,T4, Keyphasor, Thrust)
- Bearing RTD removal/install – (T1, T2, T3, T4, Thrust)
- Disconnection and reconnection of Valve LVDT / Servo
- Misc instrumentation required to be removed for mechanical disassembly of the machine.
- This scope does not include any calibration efforts
- During disassembly, perform visual inspection and physical integrity check of vibration probes, extension cables and Proximitors for functionality.
- During disassembly, inspect and check the bearing RTDs for functionality.
- During disassembly and reassembly, provide support for any removal, cleaning, and reinstallation of excitation devices including main leads, collector end brushes, shaft grounding device.