Execute testing and commissioning activities of substation equipment as per approved procedures, project specifications, and utility standards.
-
Ensure safe energization and reliable operation of substation systems.
Pre-Commissioning Activities
-
Review approved drawings, schematics, and protection philosophies.
-
Verify installation of equipment as per approved GA drawings.
-
Check cable terminations, ferruling, glandings, and tagging.
-
Conduct visual and mechanical inspections of installed equipment.
-
Ensure calibration of testing instruments before use.
Primary Equipment Testing
-
Power Transformers (IR test, TTR, winding resistance, vector group check).
-
Circuit Breakers (timing test, contact resistance test).
-
Current Transformers (CT ratio & polarity test).
-
Potential/Voltage Transformers (PT/VT testing).
-
Isolators and earthing switches.
-
Busbar continuity and insulation resistance testing.
-
Perform SF6 gas pressure and leakage checks (where applicable).
Protection & Control Testing
-
Test protection relays (overcurrent, differential, earth fault, distance).
-
Conduct secondary injection and primary injection tests.
-
Perform functional logic checks as per protection scheme.
-
Test control circuits, annunciation systems, and interlocks.
-
Verify SCADA signals and communication interfaces.
System Integration & Commissioning
-
Conduct end-to-end testing of protection schemes.
-
Perform transformer energization procedures.
-
Support synchronization of panels and feeders.
-
Coordinate shutdown activities for testing.