Scope of Work
  • 1 No. Garbage Chute System (Building configuration as installed)
  • Garbage collection trolleys serving the building
Service Frequency
  • Monthly preventive maintenance - 12 visits per year
  • Chute high pressure washing and disinfection - Quarterly (4 times per year)
  • Breakdown calls - Unlimited

Technical support shall be available to Building Management or security when required.

Consumables and Spare Parts

Comprehensive.

  • Contractor shall maintain a reasonable inventory of essential spare parts required for maintenance.
  • PPM consumables shall be included within the service.
Emergency Response
  • Priority 1 - Emergency - Immediate (within 2 hours)
  • Priority 2 - Urgent - Within 4 hours
  • Priority 3 - Expedited - Within 8 hours
  • Priority 4 - Scheduled - Within 24 hours
System Maintenance
  • Lubrication and maintenance of exhaust / ventilation fan.
  • Replacement or repair of door closer magnetic locks if faulty.
  • Repair or replacement of door closer hydraulic jack.
  • Hopper door welding and adjustment where required.
  • Replacement of door indicators if faulty.
  • Rectification of electrical connections within chute system.
  • Maintenance of fire door springs and fusible links.
  • Repair or replacement of control panel components.
  • Replacement of trolley wheels where required.
  • Inspection of water cleaning system.
  • Periodic inspection of chute duct, sealant, and operation.
  • Inspection of chute doors, interlocks, and safety devices.
Cleaning Services
  • Clean chute doors internally and externally floor by floor using non-hazardous chemicals.
  • Carry out internal chute cleaning using high pressure washing equipment.
  • Disinfect chute system to maintain hygiene.
  • Clean accessible chute duct manually where required.
  • Ensure safe cleaning without damage to system components.
Reporting
  • Service report shall be issued after each visit.
  • Reports shall include observations and recommendations.
  • Reports shall be acknowledged by Building Management.
Contractor Responsibility
  • Safe operation of the system
  • Hygiene maintenance
  • Proper functioning of chute system
  • Supply of spare parts under comprehensive coverage
  • Attending breakdowns promptly
Safety Policy
  • Provide proper PPE including gloves, masks, and protective clothing.
  • Secure work areas with signage and barricading where required.
  • Maintain housekeeping during works.
  • Contractor responsible for worker safety and liabilities.
Completion
  • Contractor shall ensure system is returned to operational condition after each service visit.